    Proyecto de explotación de concesión derivado de un permiso de investigación

    Strip mining project for a concession derived from a research permission

    Ver/Abrir
    DSG.pdf (7.506Mb)
    Identificadores
    URI: http://hdl.handle.net/10902/21984
    Compartir
    RefworksMendeleyBibtexBase
    Estadísticas
    Ver Estadísticas
    Google Scholar
    Registro completo
    Mostrar el registro completo DC
    Autoría
    Sañudo García, David
    Fecha
    2021-06
    Director/es
    Malagón Picón, BeatrizAutoridad Unican
    Velar Felices, Enrique
    Derechos
    ©David Sañudo García
    Resumen/Abstract
    RESUMEN: El presente trabajo integra un proyecto de explotación para solicitar la concesión derivada de un permiso de investigación con el fin de obtener un registro minero como concesión de explotación de recurso de la sección C. Inicialmente a Cementos Alfa, S.A se le aprobó un permiso de investigación en 45 cuadriculas mineras con un recurso de investigación de la sección C, obteniendo un resultado del estudio positivo. Se hallaron existencias de reservas de calizas margosas y margas como rocas industriales con gran interés minero y económico que afianzan la pervivencia de la empresa cementera al ser fundamentales en la elaboración del cemento. El proyecto desarrolla la explotación de este recurso en la zona sur de Cantabria cerca del pueblo de Mataporquera, dirección Aguilar de Campo-Reinosa a la altura del puerto de Pozazal. La explotación del recurso de dividirá en dos áreas extractivas A1 y A2. En estas dos áreas se realizaron estudios de investigación para certificar la calidad de los materiales. Se tuvieron en cuenta criterios para la fabricación del Clinker y posterior elaboración del cemento, uno de los parámetros fundamentales es el grado de saturación en cal (G.S.C). Del área extractiva A1 se obtendrá marga que aportará cal, alúmina y sílice de forma conjunta. El área extractiva A1 aportará mayormente cal. Las dos áreas extractivas serás explotadas de forma continua y simultanea siguiendo un ritmo de explotación en función de las necesidades de la fábrica cementera. Dentro de las cuadriculas mineras disponibles a explotar estas se verán delimitada por varias circunstancias; calidad, cantidad de recurso, orografía, zonas de especial protección (río, embalse, montes), líneas de ferrocarril y eléctricas, accesos de comunicación y estudios arqueológicos. Todas estas circunstancias han hecho plantearse varias alternativas iniciales que hemos ido descartando hasta delimitar las áreas de extracción. El método de explotación empleado será a cielo abierto distinguiendo para el área extractiva A1 un desarrollo combinando de explotación a media ladera y terrenos horizontales mientras que el área extractiva A2 empleará únicamente el método de explotación a media ladera, descendiendo en profundidad mediante banqueo. Se seguirá una secuencia de explotación y unos parámetros de explotación prefijados para las longitudes y anchuras de bancos, anchura y pendiente de las pistas de acceso, transporte interno y pistas perimetrales entro otros. Todo esto contará con un estudio de dimensionamiento de equipo para la elaboración de las fases previas, transporte interno y externo como para la explotación del recurso, donde podemos destacar que se realizará mediante voladura. Planteado esto se certificará la viabilidad técnica, económica y financiera utilizando un análisis de rentabilidad de la inversión que utiliza procedimientos de actualización de la inversión como son el VAN y el TIR. Se tendrán en cuenta las inversiones iniciales, previsión de gastos, costes de operación y los ingresos anuales de acuerdo con la producción planificación y la comercialización para un horizonte de 10 años. El resultado es muy positivo teniendo un plazo de recuperación de la inversión a los 4 años del comienzo de la actividad. Dicho esto, el presupuesto planteado para el proyecto de explotación descrito asciendo a un valor de dos millones seiscientos tres mil trescientos cuarenta euros (2.603.340,00€). Cabe destacar que cualquier actuación siempre ha sido proyectada siguiendo la legislación vigente tanto minera como medioambiental.
     
    ABSTRACT: This work integrates an exploitation project to request the concession derived from a research permit in order to obtain a mining registration as a concession for exploitation of a resource in section C. Initially Cementos Alfa, S.A was approved a research permit in 45 mining squares with a research resource from section C, obtaining a positive study result. Stocks of marly limestone and marl reserves were found as industrial rocks with great mining and economic interest that reinforce the survival of the cement company as they are fundamental in the production of cement. The project develops the exploitation of this resource in the southern area of Cantabria near the town of Mataporquera, in the direction of Aguilar de Campo-Reinosa at the height of the port of Pozazal. The exploitation of the resource will be divided into two extractive areas A1 and A2. In these two areas, research studies were carried out to certify the quality of the materials. Criteria were taken into account for the manufacture of the Clinker and subsequent elaboration of the cement, one of the fundamental parameters is the degree of saturation in lime (G.S.C). Marl will be obtained from the extractive area A1, which will contribute lime, alumina and silica together. The extractive area A1 will contribute mostly lime. The two extractive areas will be exploited continuously and simultaneously, following a rhythm of exploitation based on the needs of the cement factory. Within the mining grids available to be exploited, these will be delimited by various circumstances; quality, quantity of resource, orography, areas of special protection (river, reservoir, mountains), railway and electrical lines, communication accesses and archaeological studies. All these circumstances have led us to consider several initial alternatives that we have been discarding until delimiting the extraction areas. The exploitation method used will be open sky, distinguishing for the extractive area A1 a development combining mid-slope exploitation and horizontal terrain, while the extractive area A2 will use only the mid-slope exploitation method, descending in depth by means of benching. A sequence of exploitation and some predetermined exploitation parameters will be followed for the lengths and widths of banks, width and slope of the access lanes, internal transport and perimeter lanes, among others. All this will include a study of equipment sizing for the preparation of the previous phases, internal and external transport as well as for the exploitation of the resource, where we can highlight that it will be carried out by blasting. Once this has been raised, the technical, economic and financial viability will be certified using an investment profitability analysis that uses investment update procedures such as NPV and IRR. The initial investments, forecast expenses, operating costs and annual income will be taken into account in accordance with the production planning and marketing for a horizon of 10 years. The result is very positive, having a recovery period of the investment 4 years after the start of the activity. That said, the budget for the described exploitation project amounted to a value of two million six hundred three thousand three hundred and forty euros (€ 2,603,340.00). It should be noted that any action has always been planned following current mining and environmental legislation.
    Colecciones a las que pertenece
    • G2449 Trabajos académicos [154]

    UNIVERSIDAD DE CANTABRIA

    Repositorio realizado por la Biblioteca Universitaria utilizando DSpace software
    Contacto | Sugerencias
    Metadatos sujetos a:licencia de Creative Commons Reconocimiento 4.0 España
     

     

    Listar

    Todo UCreaComunidades y coleccionesFecha de publicaciónAutoresTítulosTemasEsta colecciónFecha de publicaciónAutoresTítulosTemas

    Mi cuenta

    AccederRegistrar

    Estadísticas

    Ver Estadísticas
    Sobre UCrea
    Qué es UcreaGuía de autoarchivoArchivar tesisAcceso abiertoGuía de derechos de autorPolítica institucional
    Piensa en abierto
    Piensa en abierto
    Compartir

    UNIVERSIDAD DE CANTABRIA

    Repositorio realizado por la Biblioteca Universitaria utilizando DSpace software
    Contacto | Sugerencias
    Metadatos sujetos a:licencia de Creative Commons Reconocimiento 4.0 España